(As of 12:58 p.m. December 20, 2024)
On December 12, 2023, Council awarded the construction contract of the Centre to Rikjak Construction Limited for the Base Bid of $8,966,457. Construction began on May 6, 2024, and we anticipate completion by Spring/Summer of 2025.
Work by the design team from SNMArchitect Ltd. has included stakeholder consultation, public information sessions and Council updates. The multi-use facility will be fully integrated with the existing Sandy Wickens Memorial Arena at 12 Park Lane on Sherose Island.
The Centre is designed to be more than just a sports facility. It will offer versatile community spaces for events, meetings, and gatherings, promoting social cohesion and ensuring a diverse range of recreational activities for residents of all ages. The construction prioritizes inclusivity, ensuring that the facility is accessible to everyone, regardless of age or ability. Specialized areas and programs will also cater to diverse needs and interests.
We continue to extend our heartfelt gratitude to the Province of Nova Scotia for their significant grant, which has helped make this project a reality and showcases their commitment to community development and innovation.
The new Recreation Centre will replace the aging one and ensure that we continue to provide residents with the high level recreational services and opportunities. The new facility will also add an indoor walking track to our inventory of recreational assets, helping to better meet demand as demonstrated through public consultation and the findings of our surveys.
Stay tuned for further updates on this innovative project as we work together to create a vibrant and inclusive space that will enhance our quality of life and bring us all closer together. The future of recreation in our municipality is bright, and we can't wait to share it with you!
Construction began on April 15, 2024, and we anticipate completion by July 1, 2025.
On February 7, we hosted a sod-turning cermony at the current recreation centre to mark the mark the beginning of the project.
Site work, brush cutting and demolition of the offices and a section of the bleachers began the week of May 6.
Site work and demolition of the offices and the entrance of the arena continues the week of May 27.
Site work of the parking areas conitnues and excavation of the new Centre's foundation begins. A new temporary arena office trailer has also been located next to the temporary entrance.
Site work of the parking areas is nearing completion and work on the new Centre's foundation continues.
Footing forms are constructed and concrete is poured. Construction of forms and rebar for walls begins. Drainage is installed in the curling rink parking area and gravel is placed.
Footings are complete and pouring of the perimeter walls continues. Drainage in the curling rink parking area is complete and the parking lot is ready for paving.
The elevator shaft, interior footings, grade beam and pilasters are poured. Work on the stairway wall continues and framing of the viewing area walls has begun. Underslab plumbing and electrical will begin soon.
The slab has been poured and excavation for light bases and underground conduit, along with the construction of the stairway wall by the bleachers is ongoing. Framing has begun in the viewing area, with plans to continue as steel erection gets underway. Asphalt paving and waterline installation are scheduled next, alongside further structural steel work. The removal of existing signage from the arena is also planned, making way for updated displays as construction advances.
Structural steel work has commenced, along with the layout of exterior walls. The west parking lot is being paved, and fine grading and paving are underway for the shared parking lot. Additionally, waterline installation is in progress. Looking ahead, focus will be on steel erection, continuing the layout and base track installation for the exterior walls, and completing the waterline installation.
The structural steel was squared and braced, the secondary framing for the exterior walls has continued, and the elevator shaft has been completed. Following a short holiday break, work will conitnue on secondary wall framing.